Condition surveys of all the district's roads and some footways are undertaken, in accordance with:-
- Government National Indicator NI168 Principal Roads where maintenance should be considered.
- Government National Indicator NI169 Non-principal Roads where maintenance should be considered.
- Local Indicators for condition of unclassified roads and footways
When the condition surveys are completed the Asset Management team investigate sites to prioritise and identify treatments.
The annual programme includes all types of carriageway treatments. See "Downloads" for a copy of the latest Programme of Works.
Every effort is made to guarantee this programme but there are unforeseen circumstances which may alter priorities. As such the programme should only be considered as a guide and is reviewed on an annual basis.
Alterations to Programme of Works
If, due to unforeseen circumstances, the programme requires altering or is delayed, the altered / delayed works will take place as soon as is practicable. For example, thin surfacing treatments are very weather susceptible, if this work is not undertaken within the current financial year, it will be undertaken during the following year.
Treatment Descriptions
Roads
Thin Surfacing / Surface Dressing – can be used successfully on all types of roads to provide skid-resistance, a sealed waterproof surface and a more uniform appearance. A fine stone, mixed with bitumen, is spread on the road as a finished surface.
Planing and Resurfacing – used at locations where the existing surface of the road needs replacing. A machine first removes the old surface and this is then replaced with a new material. This treatment will strengthen the road and improve ride quality.
Reconstruction – used at locations where the strength of the road has failed. The damaged areas will be removed and renewed, to restore strength and improve ride quality.
Footway
Thin Surfacing – used at locations to provide a sealed surface and gives a more uniform appearance. A fine stone, mixed with bitumen, is spread on the footway.
Reconstruction - used at locations where the strength of the footway has failed. The damaged areas will be removed and renewed, to restore strength and improve ride quality.